[1]闫亦农,刘立枝,崔慧荣.直线递进式服装吊挂生产流水线优化设计[J].丝绸,2018,55(11):111202.[doi:10.3969/j.issn.1001-7003.2018.11.011]
 YAN Yinong,LIU Lizhi,CUI Huirong.Optimized design of inear progressive hanging production line for garment[J].Journal of Silk,2018,55(11):111202.[doi:10.3969/j.issn.1001-7003.2018.11.011]
点击复制

直线递进式服装吊挂生产流水线优化设计(PDF)
分享到:

《丝绸》[ISSN:1001-7003/CN:33-1122/TS]

卷:
55
期数:
2018年11期
页码:
111202
栏目:
设计与产品
出版日期:
2018-11-20

文章信息/Info

Title:
Optimized design of inear progressive hanging production line for garment
文章编号:
1001-7003(2018)11-0067-06
作者:
闫亦农刘立枝崔慧荣
内蒙古工业大学 轻工与纺织学院,呼和浩特 01000
Author(s):
YAN Yinong LIU Lizhi CUI Huirong
 College of Light Industry & Textiles, Inner Mongolia University of Technology, Hohhot, 010080, China
关键词:
服装吊挂系统生产流水线评价指标直线递进式优化设计均衡指数
Keywords:
clothing hanging system production line evaluation index linear progressive optimized design equilibrium index
分类号:
TS941.6
doi:
10.3969/j.issn.1001-7003.2018.11.011
文献标志码:
B
摘要:
针对目前服装企业存在的智能吊挂系统应用不充分、流水线节拍不同步、设备闲置的问题。文采用直线递进式的优化方法,从服装企业实际生产运用的角度出发,对其生产流水线各工序进行重新拆分、组合,并概括总结出具体的优化方法。然后,运用直线递进式的优化方法对A公司具体的生产实例进行重新优化设计。优化后其流水线不仅生产工序得到了优化,工位数也由原来的56位减少为50位,且编制效率达到94.8%,均衡指数为34.34。研究表明:直线递进式服装吊挂生产流水线优化设计可有效提高服装流水线的生产效率。
Abstract:
For the current apparel companies, there are problems such as insufficient application of intelligent hanging systems, unsynchronized production line beats, and idle equipment. Starting from the perspective of the actual production and application of garment enterprises, the linear progressive optimization method was applied to re-split and combines the processes of the production line, and the specific optimization methods were summarized. Then, the linear progressive optimization method was used to redesign the specific production case of company A. After the optimization, the production line has not only optimized production processes, but also reduced the number of stations from the original 56 to 50. Besides, the establishment efficiency reached 94.8%, and the equilibrium index was 34.34. The research showed that the optimization design of the linear progressive garment hanging production line can effectively improve the production efficiency of garment production line

参考文献/References:

[1]王道良基于吊挂系统下服装生产流程重组及作业人员优化的研究[D]上海东华大学2006.
WANG Daoliang. A study on garment production process reorganization and operator optimization under suspension system [D]. Shanghai: Donghua University, 2006.
[2]CHEN J C, CHEN C C, SU L H, et al. Assembly line balancing in garment industry [J]. Expert Systems with Applications, 2012, 39(11): 10073-10081.
[3]MOK P Y, CHEUNG. T Y, WONG W K, et al. Intelligent production planning for complex garment manufacturing [J]. Journal of Intelligent Manufacturing, 2013, 24(1): 133-145.
[4]LEE C K H, CHOY K L, HO G T S, et al. A rfid-based resource allocation system for garment manufacturing [J]. Expert Systems with Applications, 2013, 40(2): 784-799.
[5]CHAN K C C, HUI P C L, YEUNG K W, et al. Handling the assembly line balancing problem in the clothing industry using a genetic algorithm [J]. International Journal of Clothing Science & Technology, 2013, 10(1): 21-37.
[6]李玉玲服装缝纫吊挂生产线调度技术的研究[D]郑州郑州大学2003.
LI Yuling. Research on scheduling technology of garment sewing hanging production line [D]. Zhengzhou: Zhengzhou University, 2003.
[7]裘玉英服装吊挂系统在生产流水线上的应用[J]嘉兴学院学报2008(6): 123-126.
QIU Yuying. Application of garment hanging system in production line [J]. Journal of Jiaxing University, 2008(6): 123-126.
[8]王蓓女装生产流水线的优化设计与仿真系统研究[D]山东青岛大学2009.
WANG Bei. Study on optimization design and simulation system of women’s wear production line [D]. Shandong: Qingdao University, 2009.
[9]陈洪倩服装缝制生产线的编排与优化[D]苏州苏州大学2012.
CHEN Hongqian. Arrangement and optimization of garment sewing production line [D]. Suzhou: Soochow University, 2012.
[10]赵冉服装生产标准工时的制定及流水线优化研究[D]上海东华大学2012.

备注/Memo

备注/Memo:
基金项目:内蒙古自治区自然科学基金项目(2014MS0621)
收稿日期:2018-02-12;
修回日期:2018-00-00
作者简介:闫亦农(1968-),女,副教授,主要为服装生产数字化
更新日期/Last Update: 2018-10-15